Water transmission line from "Minab" City to "Bandar Abbas" City

         This project was executed in Homrmozgan province, consisting of 106 km of steel pipeline with the dia of 1200 and 1400 mm including the access service road along with relevant structures and construction of 7 bridges for passing the pipeline from above the rivers with the total length of 2500 meters.

Client: Hormozgan Water Authority.

Consulting Engineer: Mahab Ghods Consulting Engineer

Start Date: 1992

End Date: 1997

 